Merchant Square, London

PUDLO Provides Canal Side Waterproofing Solution 

Industry-leading guarantee and outstanding quality control reduce risk for Expanded Structures Ltd.

Superior water-resistance and durability, significant time and cost savings, plus an unrivalled 20 year project warranty provided a convincing argument for using PUDLO waterproof concrete for the basement of building E at Merchant Square in Paddington, London.

A supplier and product that will share, if not absolve the contractor of a large part of the risk of achieving critical structures while providing unrivalled client protection is a rare thing. When it comes to waterproof concrete, it’s practically unheard of.

But this is precisely the construction and engineering proposition made by PUDLO and its range of BBA approved additives for waterproofing, strengthening and extending the life of concrete.

The case for using PUDLO for Building E at Merchant Square proved more than watertight for the foundation services specialist, Expanded Structures Ltd, part of Laing O’Rourke.

Paddington Basin

Developed by European Land, Merchant Square is a 1.8 million sq/ft mixed use scheme comprising six stunning buildings set around a major new canal-side square on four acres to the north east of Paddington Basin.

The largest commercial building within the development, Carmine has been  designed by architects, Mossessian & Partners, in collaboration with Perkins+Will, and towers 15 storeys over the Grand Union Canal.

Above ground, it provides 262,163 sq ft of grade A office space and ground floor retail, with a health club and car park facility in the 75m by 55m plan basement.

Warranty

PUDLO modified concrete carries a 20 year project warranty, effectively assuring performance and workmanship for the same period.

Crucial to this warranty is the comprehensive service support provided by PUDLO Site Support Team inspectors. The use of PUDLO additives is project-managed by these experienced technicians who provide quality control of the application, from concrete design, batching and mixing,  to site preparation, pouring, and postcure.

Building E required a critical standard of waterproofing, incorporating both lift pits and a swimming pool three levels down.

Intrinsic

PUDLO waterproofing is intrinsic to the concrete, eliminating the time, labour, deliveries and additional equipment involved in laying a waterproof membrane.

The basement construction would have involved cutting and fitting membrane material around numerous pile caps and drainage pop-ups, leading to genuine concerns about creating possible areas of weakness.

Space was restricted, so eliminating the installation of a membrane eased the complex logistics of managing the basement programme. Plant and equipment could track around freely without risk of damage to the material. Just a piece of rebar, if dropped, can tear membrane material, resulting in a water path and potential defects in time.

Simplicity

The final design called for substitution of all of the membrane in the basement slab with PUDLO, based on the simplicity of using one system and the benefits of the warranty.

In addition to supplying materials, PUDLO’s service is reassuring for specifiers and clients alike. It includes close attention to the concrete mix and specification details, as well as site inspections, attending the pour, and taking on the responsibility for achieving an effective installation.

PUDLO’s proven performance worldwide coupled with the on-site service and back-up, provided justification and peace of mind for selecting PUDLO as the waterproofing solution throughout the project.

Strength

Although PUDLO was used primarily for its waterproofing properties, its strength characteristics provided an added reassurance.

As well as lining and filling pores, PUDLO alters the micro-structure of concrete to provide significantly increased factors of dimensional stability, waterproofing and strength. It provides over 20 times greater water impermeability than the next best competing waterproofing additive, and improved 7 and 28 day concrete strengths by almost 50%.

Pouring conditions were difficult in some areas, with concrete being pumped over 100m through twists and turns and down several levels. But thanks to PUDLO’s fast-forming strength properties, as well as its excellent workability, texture, plasticity and flow characteristics, early access was gained onto the slab.

Top-Down

As well as incorporating some of the largest floorplates in the West End, building E at Merchant Square has used ‘top-down’ construction. This involved a slightly different progression of structural detail. PUDLO’s site support team worked with the contractor and ready mix concrete supplier to ensure that the design detail of the concrete mix and delivery schedule worked with the construction programme.

Firstly, the ground floor slab was constructed over the fully scanted piled basement. With the piles having the capacity to hold at that height, a 10m wide ring slab was constructed around the perimeter to act as a propping slab giving temporary support to the secant until construction could, be tied into the ground floor. Effectively, it creates a solid box around basement construction.

Top-down construction was preferred because traditional construction would have involved a mass of sacrificial propping. By putting in the concrete slab, progress was made simultaneously above and below, and the slab was retained as a structure, resulting in less wastage.

The sequence of construction involved completion of the pile caps to the three lift and stair cores first, so work on these could progress to upper levels while basement work got underway. As a result, the cores were completed about the same time as the basement.

Building E was completed in 2009 as part of first phase construction at Merchant Square, with full scheme completion in 2012.

Client: European Land & Property Limited

Consultant: WSP